Mar 14, 2024

Eine Nachricht hinterlassen

(1) When the substation is installed on site, attention should be paid to the protection of the paint on the surface of the cabinet, and collisions, cracks, etc. between the handles of the barometer, oil level gauge, thermometer, plug-in fuse and insulating pipe components are not allowed, and the screws are not loose.

(2) Clean the dust and dirt outside the substation, inside the cabinet door and on the surface of the insulation sleeve.

(3) Check the nameplate data of the substation, whether the product certificate is consistent with the order, and check whether the documents and spare parts are missing according to the packing list.

(4) The surface of the concrete platform should be flat. The combined substation is fixedon the platform by pressing plates;

(5) The form of the ground bar and the cable fixing bracket can be

(6) Cable fixing frame and grounding should be pre-buried

(7) The location of the inlet and outlet cable holes depends on the specific situation;

(8) After the Compact substation transformer is installed, there must be a gap of not less than 1.5m on the front of the switch. for operation.

(9) Grounding can use 12 galvanized or 40Xx4 galvanized round steel,Made of flat copper, the grounding resistance should meet the requirements of the power department

(10) The connection of Compact substation transformer and foundation platform is by welding.

compact substation transformer